Client: Connect Vending
Project: Office expansion by adding a Mezzanine floor over a Bank Holiday weekend

Background:
Connect Vending occupy industrial space in Oxfordshire and had a ground floor office with wasted space above it. They needed to expand and we put forward a innovative scheme to install a mezzanine floor above their occupied space out of hours with no downtime.
Scope:
> Occupied space fit out with installation of mezzanine floor into occupied space over 4 day bank holiday weekend with no downtime to the business.
> Fit out
> New furniture
Services:
> CDM, Health & Safety Duties
> Office Relocation / Churn
> Project Management
> Structural Modifications
> Space Planning & Design Consultancy
Design:
> Break out & Tea Point Facilities
> New Toilet and Shower Facilities
Construction:
> Air-conditioning modifications
> Mezzanine Floor
> Carpeting
> Decorating
> Frameless glazing
> Partitioning
> Suspended ceilings
> Voice & data installation
> Wall finishes
Furniture:
> New desking, seating & storage
Client comment:
“We were delighted with the scheme Space-pod put on the table to use our double height wasted space to install a mezzanine above our existing office space. We were even more surprised when they came up with a scheme to carry out all the disruptive works over a single bank holiday period ensuring our staff had no downtime at all.”
Download Case-study as a pdf (611k)
Link to Connect Vending